One bid covers evening work and debris removal. Another leaves both items to you. If you compare only the totals, the lower price can look attractive right up until you need to book the elevator, pay for handling or relocate staff. Put every bid on the same basis before signing.
Send every bidder the same package
Identify the drawing revision and date. Attach a short scope, the address, permitted work hours and building rules. Say what your team will supply, such as furniture, appliances or IT equipment. If a question on the walkthrough changes the scope, share the answer with every bidder.
Line up the items that move the price
Use the same rows in a comparison sheet for each bid. Enter the price where one is given and ask about any blank row.
- Access and protection. Elevator bookings, parking, protection of common areas, work-zone separation and cleanup.
- Building systems. Who moves the ductwork, connects equipment or brings services back online after a shutdown?
- Finishes. Quantities, specified materials, surface preparation and touch-ups.
- Excluded or unconfirmed work. Record who owns the item, what has been assumed and when the price can be confirmed.
An allowance is a provisional amount. Ask what quantity or product it covers and how any difference will be handled. If two contractors have priced different finishes, ask for the same product or performance before comparing.
Check the job conditions behind the price
Ask for a schedule and the assumptions behind it, including site access, material delivery and decisions due from your team. Verify the company and its licence with the RBQ. Ask one practical question about surprises. “If a duct needs to move after the ceiling comes down, who describes the change, who prices it, and who approves it?” RBQ guidance on checking contractor licences, in French

Get the answers into a revised bid
Keep the clarifications in the revised bid or a dated addendum. You can then compare scope, price and dates on the same lines. If there are still several unknowns, ask which ones a technical walkthrough could resolve before you book the work.